Dear forumist.
Am a bit baffled, I went a customer house earlier to advice on electrical installation for an external shed.
I said to them they will need a new circuit and obviously need an EIC certificate.
I went to check on CU board but all I could find was as attached photos. One biggish old mems main isolator and small where all power and lights come from.
I have tried to locate another CU in the whole 3 bedroom semi with no joy. Do one of you longtime experience sparkie know where else to check, if nothing else available is this configuration acceptable?
Am struggling to add the photos, i will try in a seperate thread
 
not part p then !
That too, however the company I work for are.
On this, time constrain will be the main factor.
So what did you suggest regarding the shed?
As I initially didn't know about the Mems isolator I told them, I won't be undertaking the shed project until the hoise bit is sorted, however he said he will be talking to his friend who install his cctv and he will let me know.
He also believe the house elecytic were done 3 year ago before buying the house and the wife have all the the certificates.
 
why is everyone jumping on rewire? are cables VIR or PVC? any testing of circuits done? OK a shiny new CU with eaerthing and bonding upgraded. pre=tests will show whether or not a rewire is needed.
Spot on telectrix, they are PVC from the point I could see.
I also mentioned maybe we can start with EICR to get direction of the next step.
 
I came to these on my one job not long back...even with a helpful note from a time when i expect some on here were wee apprentices

[ElectriciansForums.net] Consumer unit (main board)


[ElectriciansForums.net] Consumer unit (main board)
 
Is a couple of weeks not too much? at the moment I rewire lights and change the box and test within 12hrs with appretice
2 bedroom flat.
Kitchen 1st fixing 4hrs, or that what time we are given from the office..
2 weeks is about right when you have to roll up carpets, shift furniture, cut flloorboards etc.
 
#38. There's the asbestos we were talking about!

The corrections made to my earlier post about snipping the cables? Yes of course, turn the power off first. Silly me for assuming a non professional would be doing the works and not be following safe isolation procedures.

Is it a bit unfair to criticize the OP for not knowing these old style boards? You don't come across them very often now.
 
#38. There's the asbestos we were talking about!

The corrections made to my earlier post about snipping the cables? Yes of course, turn the power off first. Silly me for assuming a non professional would be doing the works and not be following safe isolation procedures.

Is it a bit unfair to criticize the OP for not knowing these old style boards? You don't come across them very often now.
Deleted there seems to be somethig up with my device thismorning
#38. There's the asbestos we were talking about!

The corrections made to my earlier post about snipping the cables? Yes of course, turn the power off first. Silly me for assuming a non professional would be doing the works and not be following safe isolation procedures.

Is it a bit unfair to criticize the OP for not knowing these old style boards? You don't come across them very often now.
It's wrong to offer advice to someone who has lmited or no experience of electrical work, in one of Gakure's post, he mentioned that there were electrical certificates form work done about 3 years ago, that in itself seems odd judging from the photos provided.
If you take into account of how he intends to do this work, and how long he thinks it will take, it becomes even more of a problem, Gakure has mentioned his Boss, wonder what his experience is? You then have the language problem, not Gakure fault, I know I, along with many of the Forum members, would struggle to converse in any foreign language, for these reasons, I asked the question regarding experience, there was never any criticism, just an
honest doubt in his ability to contemplate takng this work on, and the stream of posts has led me to believe that Gakure is so far out of his depth, and shouldn't even try ato do this work, or it's someone winding the Forum up. I hope Gakure will take note of this, and not treat it as a mickey take.
 
Deleted there seems to be somethig up with my device thismorning

It's wrong to offer advice to someone who has lmited or no experience of electrical work, in one of Gakure's post, he mentioned that there were electrical certificates form work done about 3 years ago, that in itself seems odd judging from the photos provided.
If you take into account of how he intends to do this work, and how long he thinks it will take, it becomes even more of a problem, Gakure has mentioned his Boss, wonder what his experience is? You then have the language problem, not Gakure fault, I know I, along with many of the Forum members, would struggle to converse in any foreign language, for these reasons, I asked the question regarding experience, there was never any criticism, just an
honest doubt in his ability to contemplate takng this work on, and the stream of posts has led me to believe that Gakure is so far out of his depth, and shouldn't even try ato do this work, or it's someone winding the Forum up. I hope Gakure will take note of this, and not treat it as a mickey take.
Thanks Pete as I said, am brought up to respect and listen to my elder, any advice may it critics or bashing, it good for my knowledge collection.
I will be lying to say that am experience or knowledgeable enough as that will be cocky.
When i said couple of days I didn't 2 days literally.
In between our thread I contacted the client, that when he said they got document of work done 3yrs ago and hence why I shared after.
Regarding H/S and isolation, since 90s I have worked, design, install, commission and project manage backup power station in different part of globe hence am aware of the dangers around.
Anyway, i sincery appreciate your inputs.
 

Reply to Consumer unit (main board) in the UK Electrical Forum area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
664
  • Sticky
  • Article
Good to know thanks, one can never have enough places to source parts from!
Replies
4
Views
1K
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
2K

Similar threads

  • Question
What is the distance from the point outside the house to the shed?
Replies
8
Views
824
  • Question
IMO Better to do something about those ignoring regulations first! Current system is like having a speed limit but not enforcing anyone without a...
2
Replies
20
Views
2K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top