conrad
-
upgrade to a 1940s ish installation mains busbar due to soldered joints failing on busbar isolator, 20 ish switched fuses of the same age on it. Large installation(hotel) that never closes and has alot of c1s on existing out of date certs but they want the mains upgrading 1st before the rest of the installation is dealt with... How would you go about reenergising knowing there is alot of non compliances throughout the installation. Would you be certifying and noting exclusions from regs and noting what you have done. At the end of the day you are improving the installation and the client is agrewing to get through all requirwd works in due course. Ive wrote enouvh for now lol