I wonder if anyone could assist with this query please ? I am a newbie, so any guidance or alternatives would be greatly appreciated.
I need to run a ring final partly against a wall with internal 25mm Celotex type insulation. The additional Celotex being needed due to reduced cavity insulation. Diagram below ! Also fyi, the Celotex and board are separate, not ‘backed’.
I’m trying to decide whether to “1”- clip to the thermal block, flush (with capping), under the Celotex; or “2”-go between Celotex and board, and consider the respective pro’s and con’s of each. …or any other options ?
I’m not 100% sure from the BBB what the reference method would be for the first route. Possibly 103 ? which would affect my ccc somewhat.
Taking route 2 would (might?) need me to channel slightly into the Celotex which is also frowned upon. ….What would you do ?
I need to run a ring final partly against a wall with internal 25mm Celotex type insulation. The additional Celotex being needed due to reduced cavity insulation. Diagram below ! Also fyi, the Celotex and board are separate, not ‘backed’.
I’m trying to decide whether to “1”- clip to the thermal block, flush (with capping), under the Celotex; or “2”-go between Celotex and board, and consider the respective pro’s and con’s of each. …or any other options ?
I’m not 100% sure from the BBB what the reference method would be for the first route. Possibly 103 ? which would affect my ccc somewhat.
Taking route 2 would (might?) need me to channel slightly into the Celotex which is also frowned upon. ….What would you do ?