I carried out an EICR in this flat above a shop.
Incoming supply is old, single insulate tails (fabric covered stuff) possible double pole fusing, and service fuse carrier is really loose on a badly finished wall. UK power networks are saying its not their responsibility as they only take responsibility up to the incoming fuse. So who would have installed the second fuse? I thought risers were usually adopted up to the service fuse?
Supplier say its not their responsibility either, only the tails between the fuse and meter.
DNO have said to use a contractor on the Lloyds register which Ive never heard of.
Pics attached.
Are they correct?
Incoming supply is old, single insulate tails (fabric covered stuff) possible double pole fusing, and service fuse carrier is really loose on a badly finished wall. UK power networks are saying its not their responsibility as they only take responsibility up to the incoming fuse. So who would have installed the second fuse? I thought risers were usually adopted up to the service fuse?
Supplier say its not their responsibility either, only the tails between the fuse and meter.
DNO have said to use a contractor on the Lloyds register which Ive never heard of.
Pics attached.
Are they correct?