I've just been looking at a job that has been installed by another company.
One thing I've noticed are the feeds to 2 BMS / Plant panels. They have run in 2 x 150mm 4C and doubled up on the main switch in both panels. No separate CPC has been installed and the banjos aren't earthed either.
If this had been myself I'd have run in a separate CPC and bonded the Banjos.
Thoughts please is this to regs or does it need a separate CPC ?