g99

  1. S

    Best way to maximise export of generated electricity?

    I hope to install an 8kw panel array. I have spoken to 2 installers who both seemed a bit cagey about maximum export on a G99 Fasttrack application. In short one says I am limited to 3.68kw (which I thought was automatic on a G98) the other said 7.68kw but was selling a 5kw inverter on the...
  2. M

    G99 GSI-3 4.4 kw Victron inverter install

    G99 GSI-3 4.4 kw Victron inverter install with EES and batteries and installer can set the export lint if required by dno As part G99 GSI-3 you required carry out phase to neutral loop impedance and phase to earth loop impedance test not a problem. but the must be 180 m ohms or less for...
  3. V

    g98 or g99?, larger than 3.6kw but with export limitation

    hi if a pv system with battery storage say has an inverter of 7.5kw but has export limitation built into the inverter or installed as a seperate device and is set to limited to 3.6kw export, can this still come under g98 and be notifed to dno within 28 days of commisioning? or does it have to be...
  4. T

    G99 Commissioning - Form A2-4 requirements

    I am just checking through the information I need to enter for the UKPN SmartConnect site following the commissioning of my PV/Battery system, this is a G99 system and I have approval from UKPN. Most of it is clear however I am not sure what I need to provide to answer this question ' Proof...
Best EV Chargers by Electrical2Go! The official electric vehicle charger supplier.

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Daily, weekly or monthly email

Back
Top