Guys i got my 2391 practical on friday & was wondering when R1+R2 on a 3 phase motor,
i would test seperatly across each line & cpc fromt he ccu to the supply side of the unit & then from the load side to the actual starter & the add the amounts together giving me 3 R1+R2 readings(1 for each phase)but as far as when i fill the schedule of tests sheets would i for example use the highest reading of the 3 or would i have to put in 1 for each phase therefore usung up 3 lines of the test sheet?
Also when doing an IR test on the motor circuit should i only test up to as far as the supply side of the contactor?
Many Thanks
i would test seperatly across each line & cpc fromt he ccu to the supply side of the unit & then from the load side to the actual starter & the add the amounts together giving me 3 R1+R2 readings(1 for each phase)but as far as when i fill the schedule of tests sheets would i for example use the highest reading of the 3 or would i have to put in 1 for each phase therefore usung up 3 lines of the test sheet?
Also when doing an IR test on the motor circuit should i only test up to as far as the supply side of the contactor?
Many Thanks