Hi there,
I am installing a 50 kW PV system on a barn roof. The barn is supplied by a 4 core 16mm SWA which is partly run underground and is 100 meters in length.
The three phase DB in the barn only supplies the lighting in the barn, all the old circuits have been removed becuase they wasn't being used. So this means most of the PV power will go back down the cable to the origin. There are three other buildings fed off of this point, so the PV should go to good use and not to the greedy energy companys.
the system will be around 16.6 kW per phase and about 80A per phase,I have been trying to calculate whether the cable is big enough to carry all this power over this length.
Getting a little bit stressed with it because it looks to me to be boarder line but don't wont to get this wrong. Anyone got any advice?
Nick
I am installing a 50 kW PV system on a barn roof. The barn is supplied by a 4 core 16mm SWA which is partly run underground and is 100 meters in length.
The three phase DB in the barn only supplies the lighting in the barn, all the old circuits have been removed becuase they wasn't being used. So this means most of the PV power will go back down the cable to the origin. There are three other buildings fed off of this point, so the PV should go to good use and not to the greedy energy companys.
the system will be around 16.6 kW per phase and about 80A per phase,I have been trying to calculate whether the cable is big enough to carry all this power over this length.
Getting a little bit stressed with it because it looks to me to be boarder line but don't wont to get this wrong. Anyone got any advice?
Nick