OK, just a little lighting fault for the learners among us to ponder on.
standard 2 way switching, 1 light. 3 core from sw1 to sw2, and switch wire from light in L1 and L2 of sw1.
job was to fit intermediate switch for customer's convenience.
removed 3 core from sw1 and diverted to intermediate switch, then new length of 3 core to sw2.
powered up and light on permanently, slight flicker when operating any one of the switches.
clue: the fault was of my own making, took 10mins to find, and would not have happened before 2006.
let the young 'uns have a crack before the experts try.
standard 2 way switching, 1 light. 3 core from sw1 to sw2, and switch wire from light in L1 and L2 of sw1.
job was to fit intermediate switch for customer's convenience.
removed 3 core from sw1 and diverted to intermediate switch, then new length of 3 core to sw2.
powered up and light on permanently, slight flicker when operating any one of the switches.
clue: the fault was of my own making, took 10mins to find, and would not have happened before 2006.
let the young 'uns have a crack before the experts try.