K
Kram
We have a 50kw install ready to start for a customer DNO accepted along with planning. Would really appreciate advice, we are using 3x SMA tripower 17000TL which have the G59/2 certs required by the DNO and they have told us that they will not need to witness the connection. Do we still require a G59-2 Isolation Relay Control Box, any other advice would be greatly appreciated.