B
Bendy
I need some help to clear up a couple of issues I have when aadding additional consumer units for garAge or pv installation.
1. Can smaller tails than the incoming ones be daisy chained from the existing cu to the new one as long as they are rated for the new cu. (16a and 6a) eg 4mm. I'm assuming that the mcbs in the new cu protect the cable from overload and that the main fuse will protect the cable from short circuit.
2. If I cannot fit additional tails into the existing cu and split the existing tails( assuming an isolator is fitted because obviously I would never pull the main fuse to do this:smile5 on many jobs there is not enough length to do this and as I wouldn't want to open the meter so I would need to change the tails into the existing cu. My question is if I am only changing the tails what testing would I have to do other than earths on the existing cu? One spark I know is telling me I would have to test every circuit in the existing cu and claim responsibility for it.
3. Obviously i need to check the service bonding on these installs and I know that they both need to be bonded in 10mm back to the MET. My query on this is why could I not earth a service on the other side of the house with a rod? What is the reasoning behind a single earth?
Thanks for you help
Ben
1. Can smaller tails than the incoming ones be daisy chained from the existing cu to the new one as long as they are rated for the new cu. (16a and 6a) eg 4mm. I'm assuming that the mcbs in the new cu protect the cable from overload and that the main fuse will protect the cable from short circuit.
2. If I cannot fit additional tails into the existing cu and split the existing tails( assuming an isolator is fitted because obviously I would never pull the main fuse to do this:smile5 on many jobs there is not enough length to do this and as I wouldn't want to open the meter so I would need to change the tails into the existing cu. My question is if I am only changing the tails what testing would I have to do other than earths on the existing cu? One spark I know is telling me I would have to test every circuit in the existing cu and claim responsibility for it.
3. Obviously i need to check the service bonding on these installs and I know that they both need to be bonded in 10mm back to the MET. My query on this is why could I not earth a service on the other side of the house with a rod? What is the reasoning behind a single earth?
Thanks for you help
Ben