Called today to do 2nd fix on an extension, 14 downlighters in the ceiling. On 1st fix I spoke to the builder and said leave the cable above ceiling and I will drill the holes. Could you make sure the cables for each light are below the Celotex and could you cut a section of the Celotex away for each light?
No problem he says.
The customer said he did cut out a section of Celotex for each light but they were all in the wrong position! I had done a drawing on the wall with measurements on it!
Spent hours with a pad saw and then more time with an inspection camera trying to find the cables!:mad:
 
On the plus side the weather has been great here and I've been working out side
[ElectriciansForums.net] Blo*dy Builders!!!!!!!!!!!!

.
yes baby .
 
I hate it when that happens!

I now get a big fat black marker pen and draw an 8 inch circle with an X in the middle on the ply ceiling to make it real simple for builders to understand exactly where the
Downlighters will be

They still dont get it right all the time though!
 
Have you considered using the plasterboard indicators?
Trade name ‘plasterspot’
We use them all the time, cost approximately 20p each.
They sound good...red spot after plastering, eh?
Be great if they gave a beep out, too.....for those of us with diminishing eyesight....who can still hear, of course ;)
 
The customer said he did cut out a section of Celotex for each light but they were all in the wrong position! I had done a drawing on the wall with measurements on it!
Bleedin' 'ell TC...….don't tell me you drew a drawing on the wall..... where he side stacked the plasterboard...….:oops:
 
I insist on drilling the holes before skimming or i am not liable for making good later (the plasterers i use do not mind the holes being about but some the builders use do)
Our LABC are starting to crack down on holes in the celotex above downlights to stop cold spot and are requiring at least 100mm above the fitting.
ie 100mm between the timbers 50mm counter batten then 50mm celotex.......... so far depends on the inspector
 

Reply to Blo*dy Builders!!!!!!!!!!!! in the UK Electrical Forum area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
378
  • Sticky
  • Article
Good to know thanks, one can never have enough places to source parts from!
Replies
4
Views
949
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
1K

Similar threads

  • Question
If you have a plan for the downlights, and all you are doing is cutting out and fitting them then yes, 8 downlights in 4 hrs is slow. Fixed price...
2
Replies
22
Views
3K
  • Question
Thanks Bennie. Yeah I have Oslo microwave sensor 2D type fittings which I was hoping to use. So permanent supply to all this would suffice? Thanks
Replies
10
Views
2K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top