Hi
I recently done a condition report on a domestic property with a garage separate to the house and the oil pipe runs thoough the garage and into the house to the boiler
the questions is am I right but saying the previous electrician using a 6mm 2core SWA to supply a consumer unit with 16A socket radial and a 6A lighting circuit then using the earth from the Armourings (which is connected to the consumer unit) to then bond the oil incorrect im sure it's suffie ct enough for the circuits but needs a separate Earth for the oil, or bond it at the house end instead ? can anyone share knowlege on it ?
I recently done a condition report on a domestic property with a garage separate to the house and the oil pipe runs thoough the garage and into the house to the boiler
the questions is am I right but saying the previous electrician using a 6mm 2core SWA to supply a consumer unit with 16A socket radial and a 6A lighting circuit then using the earth from the Armourings (which is connected to the consumer unit) to then bond the oil incorrect im sure it's suffie ct enough for the circuits but needs a separate Earth for the oil, or bond it at the house end instead ? can anyone share knowlege on it ?