Dear all I wonder if you can help please:-
I have a customer on a farm who has 3 x 5 total 15Kw of wind turbines installed foc by wind crop, I am assumining windcrop claim the deemed export rate of 50% of the wind FIT meter reading.
The customer has now been in touch with me as he would like to install 27Kwp of PV on his grain Barn purchasing the system.
I am confused about whats best for the customer as he has got a very small electrical load I assume there are two possibilites :-
A) is he allowed to go for the deemed export option of 50% of his PV FIT meter reading as he is less than 30Kw of PV, bearing in mind he has 15Kw of Wind.
B) If an export meter is fitted at the origin surely it will be measuring some of the exported wind generation units as well as the exported PV generation units ?
If any one has addressed this scenario or has some solutions it would be greatly appriciated.
Thanks in anticipation
I have a customer on a farm who has 3 x 5 total 15Kw of wind turbines installed foc by wind crop, I am assumining windcrop claim the deemed export rate of 50% of the wind FIT meter reading.
The customer has now been in touch with me as he would like to install 27Kwp of PV on his grain Barn purchasing the system.
I am confused about whats best for the customer as he has got a very small electrical load I assume there are two possibilites :-
A) is he allowed to go for the deemed export option of 50% of his PV FIT meter reading as he is less than 30Kw of PV, bearing in mind he has 15Kw of Wind.
B) If an export meter is fitted at the origin surely it will be measuring some of the exported wind generation units as well as the exported PV generation units ?
If any one has addressed this scenario or has some solutions it would be greatly appriciated.
Thanks in anticipation