working on a job which is a large refurbished building on 3 levels
when a wing is finished the board serving it is livened up and
the lighting and power for that wing is left on after local testing
however no protective bonding has been carried out yet to any services
that require it.The building has extensive metallic pipes,gas ,water ,heating etc
which links to all areas ,all not bonded,plumbers still working on pipes off
main pipe work.
firm taking no notice of concern I raised about it when I heard of the plans to do this
what would you do.
when a wing is finished the board serving it is livened up and
the lighting and power for that wing is left on after local testing
however no protective bonding has been carried out yet to any services
that require it.The building has extensive metallic pipes,gas ,water ,heating etc
which links to all areas ,all not bonded,plumbers still working on pipes off
main pipe work.
firm taking no notice of concern I raised about it when I heard of the plans to do this
what would you do.