I've got my practical exam on wednesday and was just wondering when testing a ring main should you always cross connect R1 to RN before doing R1 to R2?. Is there a set sequance.
So far i have
Continuity of cpc and main earthing conductors
Continuity of ring
End to end
Cross connect R1 to RN
Cross connect R1 to R2
Insulation Resistance
Polarity Dead