I am installing a commercial food premises at the moment, the shop fitters have asked me to bond all steel work, can someone confirm which of these need bonding please:
- Suspended Ceiling Grid - 2.4m High
- Commercial Oven - Connected through 4mm SWA to commando and 6mm flex to oven
- Fixed Steel Fridge Counter - Connected via 13A Plug - 2.5mm Earth
- Fixed Steel Counter - Bolted to the above fridge
- 2 commercial fridges - connected via 13A Plug
- Serving Counter - Wired directly into the DB with 4mm T&E (Earth 2.5mm)
- Preparation Table - No Bonding - No direct connection to mains
- Commercial Sinks - >1m away from any electrical outlet and plumbed in Copper - Bonded with 10mm Earth