Hi, I came across an install where the equipotential bonding to the pipes feeding the boiler had been taken from the spur providing the power to it. It was run as a separate 10mm earth wire from the fuse box (connected to the earth terminal inside) and cable tied to the power flex going to the boiler. I checked the equipotential bonding from the MET to the gas/water service pipes and they were in place and correct. I'm wondering why this additional earth wire was run to the boiler pipes in the way that it has been and whether it represents a danger in the case of a live to earth fault as it seems to be a part of the electrical wiring installation and not as part of the equipotential bonding. At the boiler end it is daisy chained across the pipes.