Hi guys, I'm not into EICR's but would like to ask your opinions on this situation. GPR enclosure with locked doors. Several SWA cables emerge from ground within the enclosure but glanded in free air. All glands have banjos and locknuts on and are all cross bonded together. The cores from the SWA's then go directly to customers own meters within the enclosure. RE termination of the SWA's should that be classed as not mechanically safe / sound?
Re cores of the SWA going straight to the meters, should they been double insulated ie heat shrink? Whilst it has been like this for some time, it look aweful, it all test out ok.
Re cores of the SWA going straight to the meters, should they been double insulated ie heat shrink? Whilst it has been like this for some time, it look aweful, it all test out ok.