Guys thanks for quick reply. Really appreciated that.
Well for the new build for lighting load (2.5W) is 17.76 Amp, Instantaneous heater (3kw) - 13.04 Amp, Hand dryer (1.5W) - 6.52A, Electric heater (1500w eachx3) - 14.78A and ring main 32A which gives 82.1A (round up 100A max demand) in total. The existing one has 8 way 3 phase DB. Consist of 1. (R-16A, Y-16A & B-6A), 2. (R-32A, Y-16A & B-6A), 3. (R-16A, Y-6A & B-16A), 4. (Spare), 5. (R-16A, Y- spare (where it was initially proposed to supply the new build, but now it is not possible as new current demand is 82.1A & B- 40A), 6. (Spare), 7. (R-Y-B- 16A each) and 8 & 9 are both spare. The main supply is probably from
feeder pillar (Merlin Gerin Type 630 - BS BSEN 60947 IE 630A). The size of the cable is
4 core 35mm2 to existing building (400V 63A Isolator). The one with bold, I am not sure about it cause I was verbally mentioned by 3rd person.
The size of the building is 99mm2. It has i think 10 double socket out. Is 32 Amp MCB is enough to protect it?
Hopefully I can get rigid information in few days time.
I have a small building to design. The main supply is from another building (existing) which is 3 phase and 63A protection (not sure about it). It is 7 way and 3 are spare. L1 is 96A, L2 is 54A and L3 is 84A. I am looking forward to use L2. But the new building have a load of 82.1A and probably require 100A protection. I think L2 is not big enough for the new one. Can some one fire any idea weather to get a new 3 phase line or use one of 3 spare and distribute the load across. Can existing building (3 phase 63 A) enough to take this new load?
Any one have any thought about it?
i tried to switch to the architecture one but I failed it. Spent 30 min on it still not succesful.