belmontbuild

Hi all,

I am doing up my flat, which is quite a large space, about 150 spot lights and 65 plug sockets (now 95).

My Electrician started on monday and went home Thursday afternoon. He emailed me last night saying he is not willing to come back because I agreed to pay him 3.1k upfront on monday however I did not manage to get the money to him until tuesday which to be honest was my fault however I do feel its a little harsh to quit a job half way through because of that. I think he has just found another better paying job.

NB: job was 7350 first fix and 5k second fix. He is going to keep the ÂŁ3.1k I have paid him and so far he has run 6 ring mains and boxed up 90 ish plug sockets.

Anyway what are my choices now? Unfortunately this has messed up the rest of my build as I can not put my floors down until the electrical work is finished so I am going to have to cancel the other jobs that are due to start next week.

Will I be able to find someone that is willing to take on a half done job? Should I just get someone on a day rate or get someone to price for the full job again?
 
I'm a little skepticalthat this is the full story. He walked off the job after the first day because a payment that has now been received by him was a day late...and no other reason...? In that case if he hadn't received his payment why did he even start work?

I'm not understanding the boxing up of 90'ish plug sockets part. Has he installed 90'ish sockets on 6 ring circuits...in one day?
 
Hi & welcome. Sorry to hear about your situation. Seems strange that he has walked off due to deposit being a day late & also, why did he start without payment? Had you signed any sort of contract with him? At this moment, I cannot think what your best option would be. Either way its looks like other work will have to go on hold until you have sorted out your electrics situation. You may be lucky & find that someone here maybe able to help.
 
I'm a little skepticalthat this is the full story. He walked off the job after the first day because a payment that has now been received by him was a day late...and no other reason...? In that case if he hadn't received his payment why did he even start work?

I'm not understanding the boxing up of 90'ish plug sockets part. Has he installed 90'ish sockets on 6 ring circuits...in one day?


Hi sorry I was not really clear. He showed up Monday (01.10.12), I told him I would go to the bank on monday to drop the cash into his account. I was quite busy with other builders on site and did not get the chance to go to the bank so on tuesday again I was on site so I gave him the 3k deposit in cash and told him to hold onto the money until he can see the deposit in his account, I then got my business partner to do a BACS transfer into his account which showed up a few hours later so he gave me back the 3k I gave to him as security. Its not that I was not willing to pay only the logistics of getting into the bank to do the deposit.

He then worked until Thursday afternoon (04.10.12) and went home with plans to come back on monday. Sunday night I got an email say

Just a quick email to advise you that I will not be coming back up to XXXX as I was not happy in the way that you handed out the first payment or operated.
I run a professional business and do not run a cash business and that we were paid by a second party.

The work that has been carried out so far, are the six ring mains all wired and boxed to which you have paid me ÂŁ3093.75 of the first fix cost of ÂŁ7375.00 to which I have also fitted 44 additional points.

I'm not after any further payments as the works can be carried out by a second party.

So I have been on the phone this morning and got a couple of Part P guys willing to come and take a look so it should hopefully work out.


Hi & welcome. Sorry to hear about your situation. Seems strange that he has walked off due to deposit being a day late & also, why did he start without payment? Had you signed any sort of contract with him? At this moment, I cannot think what your best option would be. Either way its looks like other work will have to go on hold until you have sorted out your electrics situation. You may be lucky & find that someone here maybe able to help.

To be honest I think he just found a better offer which at the end of the day is up to him. He started without payment because he knew I was going to pay, its a huge project and I offered to give him cash on the first day (as long as I got a receipt on the books) so there was never really any questions about payment. Its just that he wanted BACS and not cash which I understand also.
 
No offence meant , but either you are telling porkies , ( which i think you are probably not ! ) or this bloke is a nutter and your best off without him !?
 
Last edited:
Have to agree,

there must be something else missing here as I cannot see a true spark walking away from a contract like that without proper cause.

Sounds good but you say a true spark remember our trade has been diluted by the Electrical Trainee and any Tom Dick or Harry who the scheme provider deems that they can badge for a fee of course so look it this way either the customer messed him about or he was out of his depth so my advise to the OP is when getting someone in ask how long they have been in the trade and have they done jobs as big as this before.

Now I walked off a job once as I was doing a PIR and fixed a couple of things free of charge but then got messed about by the customer who was holding the bill to ransom but I said I aint putting up with this and walked was not easy as the customer give me a bad review but the good thing was I had a right to reply I lost a days pay but have no complaints as I just would not take the hasle
 
Can belmontbuild please clarify if the price was based on 65 or 95 sockets. And what sort of spot lights are they?

Could be the electrician under priced the job, realised his mistake and took the opportunity to walk away without losing any money.
 
95 sockets = 'Big Space', I should blinking well think so with that many :drunk:

What the hell is it, a converted aircraft hanger?. Or are you running some sort of illicit DVD copying empire and need loads of duplicators? LOL

haha no just one huge flat. 6400sq ft

No offence meant , but either you are telling porkies , ( which i think you are probably not ! ) or this bloke is a nutter and your best off without him !?

Really there is nothing more to the story then this, I have been as honest as I can. The only thing is that the guy was staying in a hotel as its 3 hours from his home town so I assume he found work closer to home.

Can belmontbuild please clarify if the price was based on 65 or 95 sockets. And what sort of spot lights are they?

Could be the electrician under priced the job, realised his mistake and took the opportunity to walk away without losing any money.

his price was based an about 65 plug sockets and 120 (ish) light fittings, we now have 95 sockets and 210 light fittings I agreed I would pay ÂŁ25 extra per plug socket and ÂŁ20 per light fitting that was not quoted for in the original drawings (on top of the price posted above). The spot lights will be something like this

heals.co.uk/ceiling+spotlights/montana-single-spot-light/invt/514575

(NB I am not buying the above spot lights just that style)
 
Well whatever the reason was that he walked I guess we'll never know what was going through his mind to want to walk away from what sounds like a substantial contract. The question is whether he's done sufficient work to warrant the money he's been paid. If he has then I would just find another installer and start afresh, if not you'll have to get legal advice about recovering your money .
 

Reply to Electrician walked off the job half way, what now? in the UK Electrical Forum area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
275
  • Sticky
  • Article
Good to know thanks, one can never have enough places to source parts from!
Replies
4
Views
773
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
779

Similar threads

  • Question
In the mind of someone lying there wide awake at 3AM, just about anything.
    • Like
2
Replies
25
Views
2K
I'm begining to think like this now, I very rarely work for builders anymore but the couple that I still do work for are the worst payers out of...
    • Like
    • Agree
Replies
8
Views
666

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top