Scenario....
Big shop, 5 internal lighting circuits.
EM's installed as per spec, with a few on each circuit.
LE lighting used with EM conversion packs used.
How would you go about installing a test switch for EM's?
Would you
a) install key switch for each EM pack next to the converted fitting, bearing in mind that the lighting is all L/E recessed,
b) test switch at DB powered from respective circuits,
c) not bother and just use circuit MCB's as the testing will only be done during daylight hours.
Just after opinions, as i have already done it and would be interested to hear others P's.O.V
Ta
Scenario....
Big shop, 5 internal lighting circuits.
EM's installed as per spec, with a few on each circuit.
LE lighting used with EM conversion packs used.
How would you go about installing a test switch for EM's?
Would you
a) install key switch for each EM pack next to the converted fitting, bearing in mind that the lighting is all L/E recessed,
b) test switch at DB powered from respective circuits,
c) not bother and just use circuit MCB's as the testing will only be done during daylight hours.
Just after opinions, as i have already done it and would be interested to hear others P's.O.V
Ta