Hi All
My companys turnover has rapidy increased over the last 6 years and we have steadily grown from 2 ( buisness partners) to 25 sparks. We have been trading as a labour only subbie using the Lukins installation times guide and Excel to tender and win various contracts.
The company we are doing alot of our work for now want us to go down the labour and materials route and we have purchased Exreme estimating software from luckins its a bit hard to use but after the training day in 2 weeks hopefully it will speed up the tendering process.
But as I am going through the tendering process there are a couple of things that worry me about supplying the materials.
1 Is there an industry standard mark up for waste on materials ?
2 The containment drawings are not co-ordinated I am working on 30 % additional sets to the flat ones shown on the drawings is there also an industry standard for that ?
3 Copper prices have been rising rapidly and Im worried about loosing out if the price goes up after I sign the contract . Could a PC sum be the answer ?
Thanks in advance
My companys turnover has rapidy increased over the last 6 years and we have steadily grown from 2 ( buisness partners) to 25 sparks. We have been trading as a labour only subbie using the Lukins installation times guide and Excel to tender and win various contracts.
The company we are doing alot of our work for now want us to go down the labour and materials route and we have purchased Exreme estimating software from luckins its a bit hard to use but after the training day in 2 weeks hopefully it will speed up the tendering process.
But as I am going through the tendering process there are a couple of things that worry me about supplying the materials.
1 Is there an industry standard mark up for waste on materials ?
2 The containment drawings are not co-ordinated I am working on 30 % additional sets to the flat ones shown on the drawings is there also an industry standard for that ?
3 Copper prices have been rising rapidly and Im worried about loosing out if the price goes up after I sign the contract . Could a PC sum be the answer ?
Thanks in advance