A customer of mine sets up exhibitions for the like of Carlsberg, Budwiser, Hardys etc.
Each year they have been, they Hire a 400A three phase flight case distribution board, each phase has 10 RCBO's and around the back of the flight case it is loaded with 16A and 32A commando plugs.
All equipment is portable PAT Tested and plugs into the back of this flight case some items will connect into extension leads.
Wembley have now said they want an EIC for the installation.
I have advised my customer to take the PAT log of the items (everything is stickered and serialised).
I contacted the supplier of the distribution flight case and requested the schedule of test results for the RCBO's, they said it was done a few months back when it last came back to them and they will get it to my customer by email later today.
Other than that what else can be done?
How can an EIC be issued by an installation that can be changed by unplugging and replugging in portable items?
Each year they have been, they Hire a 400A three phase flight case distribution board, each phase has 10 RCBO's and around the back of the flight case it is loaded with 16A and 32A commando plugs.
All equipment is portable PAT Tested and plugs into the back of this flight case some items will connect into extension leads.
Wembley have now said they want an EIC for the installation.
I have advised my customer to take the PAT log of the items (everything is stickered and serialised).
I contacted the supplier of the distribution flight case and requested the schedule of test results for the RCBO's, they said it was done a few months back when it last came back to them and they will get it to my customer by email later today.
Other than that what else can be done?
How can an EIC be issued by an installation that can be changed by unplugging and replugging in portable items?