M
Marcosparco
Hi Hope someone can put me on the right track here as I'm going in circles.
Ok I set out to do a straightforward CU change (at home) for my ELECSA assesment - or so I thought. I'm fairly happy with testing on new circuits but these are around 15 years old.
My overall question is what level of pre work PIR is required, how much is required to be put right v's flagged with appropriate code for a CU change?
Did what I thought was the right thing and did some pre work tests and got the following issues.
1. Polarity issue at one socket - now corrected
2. 2 way switch not working - now fixed
3. Poor ins resistance in ring, but >1 Mohm, so I believe this is within limits although advise further investigation.
4. Socket positioned over sink in celler/utility area.
5. 2 light switch backboxes too shallow to allow face plate to be tightened up fully
6. missing earths to backboxes
7. looks like 6mm main bonding to gas and no label
and last but not least....
8. R1+R2 on the one ring circuit is too high (3.59 ohm).
As it's my home I'm happy putting these right as required, but where do you draw the line, especially if it is for a customer unwilling to pay for extra work?
In some ways its good this was not straightforward ( ie typical of CU changes!?), but I'm getting bogged down, so any advice would be much appreciated thanks!
Mark
Ok I set out to do a straightforward CU change (at home) for my ELECSA assesment - or so I thought. I'm fairly happy with testing on new circuits but these are around 15 years old.
My overall question is what level of pre work PIR is required, how much is required to be put right v's flagged with appropriate code for a CU change?
Did what I thought was the right thing and did some pre work tests and got the following issues.
1. Polarity issue at one socket - now corrected
2. 2 way switch not working - now fixed
3. Poor ins resistance in ring, but >1 Mohm, so I believe this is within limits although advise further investigation.
4. Socket positioned over sink in celler/utility area.
5. 2 light switch backboxes too shallow to allow face plate to be tightened up fully
6. missing earths to backboxes
7. looks like 6mm main bonding to gas and no label
and last but not least....
8. R1+R2 on the one ring circuit is too high (3.59 ohm).
As it's my home I'm happy putting these right as required, but where do you draw the line, especially if it is for a customer unwilling to pay for extra work?
In some ways its good this was not straightforward ( ie typical of CU changes!?), but I'm getting bogged down, so any advice would be much appreciated thanks!
Mark