Hi just trying to clear a question up,reg134.2.2 states the designer makes the recommendation for the first PIR to be done.
GN3 page 19 2.5 says the inspector is the person to recommend the first PIR,
which one is correct?
GN3 page 19 2.5 says the inspector is the person to recommend the first PIR,
which one is correct?