Hi,
Mainly been doing domestic installations so far, some small scale commercial still G83.
Finding it a bit of a nightmare gathering all the information and pricing I need to accurately quote for larger size systems.
I think i'm nearly there...
-We will be getting our assessors to measure and quote based on the size system;
-If the customers happy we get a Letter of Authority to apply to local DNO for G59 connection;
-Send application with relevant info on form etc and wait for response;
-Either receive decline, approval or approval with network upgrades (additional costs);
-Hopefully it is a straight approval (so should be free of charge) in which case can get to work installing said system once contract signed;
-Once installed (with approved materials) contact chosen G59 Relay supplier to install and test G59 Relay (Cost for G59 Relay and equipment + Cost for Testing) (May require witnessing by DNO at a cost);
-Send filled in (by G59 test engineer) 'Generating Plant Installation & Commissioning Confirmation' to DNO;
-If system over 30kW then export meter required, in which case;
-Contact FiT provider to find out relevant Meter Operator;
-Contact Meter Operator to fill in Half Hourly Meter Operator Contract Form which provide an Export MPAN (Cost to install + yearly meter costs);
-Register Export MPAN with FiT provider and get approval (Quarterly costs for data provision);
-Meter Operator then fits new or replaces existing Import Export Meter;
-Wait for completion of set up.
If under 50kW register with MCS, and over with RO.
I haven't specified the costs of the Relay, testing, export meter and data provision as i don't know the costs.
The question is,
Is that everything?
Or have i missed anything out that could pop up unexpected down the line or got anything wrong?
Mainly been doing domestic installations so far, some small scale commercial still G83.
Finding it a bit of a nightmare gathering all the information and pricing I need to accurately quote for larger size systems.
I think i'm nearly there...
-We will be getting our assessors to measure and quote based on the size system;
-If the customers happy we get a Letter of Authority to apply to local DNO for G59 connection;
-Send application with relevant info on form etc and wait for response;
-Either receive decline, approval or approval with network upgrades (additional costs);
-Hopefully it is a straight approval (so should be free of charge) in which case can get to work installing said system once contract signed;
-Once installed (with approved materials) contact chosen G59 Relay supplier to install and test G59 Relay (Cost for G59 Relay and equipment + Cost for Testing) (May require witnessing by DNO at a cost);
-Send filled in (by G59 test engineer) 'Generating Plant Installation & Commissioning Confirmation' to DNO;
-If system over 30kW then export meter required, in which case;
-Contact FiT provider to find out relevant Meter Operator;
-Contact Meter Operator to fill in Half Hourly Meter Operator Contract Form which provide an Export MPAN (Cost to install + yearly meter costs);
-Register Export MPAN with FiT provider and get approval (Quarterly costs for data provision);
-Meter Operator then fits new or replaces existing Import Export Meter;
-Wait for completion of set up.
If under 50kW register with MCS, and over with RO.
I haven't specified the costs of the Relay, testing, export meter and data provision as i don't know the costs.
The question is,
Is that everything?
Or have i missed anything out that could pop up unexpected down the line or got anything wrong?