Just a quick note to say that G83/1-1 Stage 1, Stage 2 and G59/2 now include formal reference to using G83/1-1 for up to 17kW/phase / 50kW 3phase (with G59 protection settings)
The ammendments are dated April, however the documents were 'authored' on the 03/05/2011 and have only just appeared on the website:
The latest guides and 'NEW' decision tree are available from the ENA Website here:
Engineering documents - Energy Networks Association
What confuses me is that it says:
I guess it is to cover the multiple install on Housing Associatin projects where it might be a whole street, so now the network sees it as a 100kWp system on a single phase...
It also says
The ammendments are dated April, however the documents were 'authored' on the 03/05/2011 and have only just appeared on the website:
The latest guides and 'NEW' decision tree are available from the ENA Website here:
Engineering documents - Energy Networks Association
What confuses me is that it says:
This implies that if you are doing a row of houses, each with their own meter, different customers, it falls under Stage 2, even if they are seperate sites.Number of premises :
In how many premises are you planning to install generating units?
If > 1 use Stage 2
I guess it is to cover the multiple install on Housing Associatin projects where it might be a whole street, so now the network sees it as a 100kWp system on a single phase...
It also says
No problem there, though in the past it was done using Stage 2, maybe this is now discretionary and won't be needed?Number of generating units
Are you planning to install more than one unit in a single premises?
Discuss with DNO