They use different forms for a start. Generally G83 is simply a case of filling out the notification form and then sending it to the DNO with a schematic and certificate - normally after the install has been carried out.

G59 uses different forms and they need to be run past the DNO before an installation is carried out.
 
i have been using G83 for 50kwp with western power. Nobody has yet pulled me up on it.
Are all inverters not rated to DNO standards anyway.
Can see the point in the big installs but 50kwp is only a small amount of power over 3phase
 
Done a few of 50kwp, thats why im confused a little
they have never said that forms are wrong soI keep sending them.
Two have gone of today so i will wait and see
 

Reply to the thread, titled "G83/g59" which is posted in the under the Solar PV Forum | Solar Panels Forum on Electricians Forums.

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

Daily, weekly or monthly email

Back
Top