lee mcgregor
I have to price a job which involves the wiring of 41 x 2kw heaters 8 x 1kw heaters 1x 3kw heater but the owner want to be able to control these via a time clock with the option of 1hr boost time . Right now they have central heating in but due to major problems the owner is wanting this stripped out .... now this comes in at 374amps roughly .....around 124 amps per phase he says he has a 400amp busbar i can come off of but im a bit concerned its a bit border line with all the other equipment thats in this offices ... im seeing it on tuesday to get a proper look at what he has , does anybody have any experience on the most important things i should be checking for ?? should i carry out load test on each phase to see what there currently pulling ...any thing else? thanks