sparkies2306
Hi guys
Need a bit of help on testing in a hotel (bit of background) its a 7 storey building with main switch room in basement as a working hotel nothing can be switched off. On the 7th floor existing rooms were refurbished with 8 new rooms added
there is a busbar trunking running up the hotel from switch room and a tap off on every floor
on each floor a 3phase board numbered (db15) which supplies power to each room then in every room there is a fuse box for all in rooms
Now i have to test all of this so testing the fuse board db15 feed to each rooms thats ok and testing of rooms ok
but testing the busbar or main switch room for my main readings for the KA, ZE, and all info for particulars of installation at origin nothing can be switched off also this hotel has no previous test info as was bought over a few years ago and no info was left
id be grateful if you could give any advice on this test procedure
could i put the 3 phase board down as the origin thats on 7th floor if i cannot get this info, would the 3 phase tap off be my main switch which is 3 x 60amp fuses which feeds the 3 phase board
thanks again guys
Need a bit of help on testing in a hotel (bit of background) its a 7 storey building with main switch room in basement as a working hotel nothing can be switched off. On the 7th floor existing rooms were refurbished with 8 new rooms added
there is a busbar trunking running up the hotel from switch room and a tap off on every floor
on each floor a 3phase board numbered (db15) which supplies power to each room then in every room there is a fuse box for all in rooms
Now i have to test all of this so testing the fuse board db15 feed to each rooms thats ok and testing of rooms ok
but testing the busbar or main switch room for my main readings for the KA, ZE, and all info for particulars of installation at origin nothing can be switched off also this hotel has no previous test info as was bought over a few years ago and no info was left
id be grateful if you could give any advice on this test procedure
could i put the 3 phase board down as the origin thats on 7th floor if i cannot get this info, would the 3 phase tap off be my main switch which is 3 x 60amp fuses which feeds the 3 phase board
thanks again guys