Hotel extension built 1989 multiple boards each serves 2 rooms,heat, light, sockets, telemetry controled heating from reception, parent board supplies sub via 4mm SWA on a 32A type 2.Sockets 20A b curve, heating 10A b lights, 10A b, sockets are ring final in 2.5/1.5 It's my understanding that has been done like this to get the Zs down otherwise it would be out with the required disconnection times, I do not have any real concerns over this, but, is this a normal approach, I would have uped the cable and supply breaker and ultimately the RF to 32A there are 36 rooms done this way so maybe cost was an factor when the job was quoted who knows any thoughts