P
Plonker 3
Got to install an new 2 way DB next to a existing DB, as need to install a new circuit and no spare ways available. But the Oil isn't bonded and the main earth needs upgrading. Once I have altered both of them how much testing do I have to carry out just a Ze and Pscc or do I have to test every circuit on the existing DB as all the characteristics will have changed?