Hi
Just had my system installed and have a few questions.
My system consists of 14 Sharp NU-R250 J5 panels and a SB3000hf invertor.
1...Why is there a 3Kw invertor on my system ? should it not be at least 3.5 or more ?
2...I was charged £360+vat for commissioning and the installer commisioned it nobody has looked/checked my system since the instal team left.
I thought commisioning was so a different pair of eyes could look at and test the work and then sign it off. Feels like paying him twice for the same job.
3...I was quoted and paid for a SB3800 and they installed the 3000hf, when asked about price difference I was told they were about the same, anybody know different ?
I stay in Glasgow roof pitch 30" and facing SSW
TIA
Jim
Just had my system installed and have a few questions.
My system consists of 14 Sharp NU-R250 J5 panels and a SB3000hf invertor.
1...Why is there a 3Kw invertor on my system ? should it not be at least 3.5 or more ?
2...I was charged £360+vat for commissioning and the installer commisioned it nobody has looked/checked my system since the instal team left.
I thought commisioning was so a different pair of eyes could look at and test the work and then sign it off. Feels like paying him twice for the same job.
3...I was quoted and paid for a SB3800 and they installed the 3000hf, when asked about price difference I was told they were about the same, anybody know different ?
I stay in Glasgow roof pitch 30" and facing SSW
TIA
Jim