Ok im currently up **** creek without a paddle!
Ive been busy on various projects in the meen time we have had a reletively small project running in the background which i havent paid much attention to as the guys i had running it are competent and i trust them..
So after a site visit and a skim through the records we are missing a large amount of site instructions which amount to 60% of the contract value.
The client knows this and is starting to play hardball, im looking at ways to rectify the situation but the only record i have of the changes are the drawing registers and daywork sheets, The question is will a drawing register count as an instruction? im assuming it will as these are changes issued by the client on sighned documents.
Any feedback welcome.
Cheers
Alex
Ive been busy on various projects in the meen time we have had a reletively small project running in the background which i havent paid much attention to as the guys i had running it are competent and i trust them..
So after a site visit and a skim through the records we are missing a large amount of site instructions which amount to 60% of the contract value.
The client knows this and is starting to play hardball, im looking at ways to rectify the situation but the only record i have of the changes are the drawing registers and daywork sheets, The question is will a drawing register count as an instruction? im assuming it will as these are changes issued by the client on sighned documents.
Any feedback welcome.
Cheers
Alex