fezzie
Hello all.
I have just completed my first install (awaiting Napit MCS inspection next month).
Can i connect to the grid, and send the commisioning forms to the DNO now?.
The DNO forms ask for accreditation/qualification, is part p registered etc ok,
and the MCS just a requirement for FIT application at a later date.
I have just completed my first install (awaiting Napit MCS inspection next month).
Can i connect to the grid, and send the commisioning forms to the DNO now?.