P
parm
Hi Guys,
I'm doing my first ring mains (kitchen) and consumer unit change on Fri, I've got LABC coming on site in the morning annd was wandering if you could give me some insight on what to expect?
The background on the install is that the kitchen was deemed code 1 on a PIR as 1.5mm cable was used for the ring and the customer has asked for a split load RCD(2X) protected upgrade at the same time. I have a copy of the PIR that verifies correct main earthing bonding and incoming earth to DB CSA size and that supplementary bonding is correct and present as per 17th Edition. I also have the DNO coming in on Monday to upgrade the meter tails to 25mm and fit an isolator prior to DB change.
Thanks in advance for the advice.
I'm doing my first ring mains (kitchen) and consumer unit change on Fri, I've got LABC coming on site in the morning annd was wandering if you could give me some insight on what to expect?
The background on the install is that the kitchen was deemed code 1 on a PIR as 1.5mm cable was used for the ring and the customer has asked for a split load RCD(2X) protected upgrade at the same time. I have a copy of the PIR that verifies correct main earthing bonding and incoming earth to DB CSA size and that supplementary bonding is correct and present as per 17th Edition. I also have the DNO coming in on Monday to upgrade the meter tails to 25mm and fit an isolator prior to DB change.
Thanks in advance for the advice.