Nearly there
Hi
basically Im a 2nd year apprentice and my boss wants to put me to the test
There is a commercial building thats single phase
The guy wants 2 temporary supplys for 2 seperate intruder alarms in one building
The run will be 100m
So far i have figured out (as yes i am lazy and i need to make a move)
I will be using 2 core SWA 4mm CLipped outside to an FCU which will be inside the building then spur off 2 x 2.5mm T+E 20metres to each side to the intruder alarms.
I will be using a 6A FCU
My boss wont help me untill i make a mistake and i just thought id ask for some help off the website ive been browsing
sorry for the basic questions =/
basically Im a 2nd year apprentice and my boss wants to put me to the test
There is a commercial building thats single phase
The guy wants 2 temporary supplys for 2 seperate intruder alarms in one building
The run will be 100m
So far i have figured out (as yes i am lazy and i need to make a move)
I will be using 2 core SWA 4mm CLipped outside to an FCU which will be inside the building then spur off 2 x 2.5mm T+E 20metres to each side to the intruder alarms.
I will be using a 6A FCU
My boss wont help me untill i make a mistake and i just thought id ask for some help off the website ive been browsing
sorry for the basic questions =/