S
Steve34
hi guys,
I was gonna do my pir in exactly the same way as i do initial verifications, unplug all loads, disconnect voltage sensitive equipment etc etc... but have been told some testers do things i found very confusing, ie:
When doing the IR test only do N-E, as any problems betwen L-N and L-E would have caused a fault and the client would've had someone round to fix that already?
Don't bother taking the earthing conductor out to do your Ze as it can be a b*tch to put back in the earth bar especially on a badly done board, the reasoning is the suppliers earth was proved by initial verification, and the system has always worked perfectly well with the parallel earth paths, also the parallel earth paths actually make your reading look better?
But the one that threw me the most was, as long as they get a good reading on sometimes as little as 25% of the install, they pass it and just right only 25% checked in the limitations, and this is acceptable?
I'm just looking for some clarification, now i know none of the professional testers on this site would do such things so i'll phrase my question as; exatly what tests would your "friend" do and how would he do them? Thanks.
I was gonna do my pir in exactly the same way as i do initial verifications, unplug all loads, disconnect voltage sensitive equipment etc etc... but have been told some testers do things i found very confusing, ie:
When doing the IR test only do N-E, as any problems betwen L-N and L-E would have caused a fault and the client would've had someone round to fix that already?
Don't bother taking the earthing conductor out to do your Ze as it can be a b*tch to put back in the earth bar especially on a badly done board, the reasoning is the suppliers earth was proved by initial verification, and the system has always worked perfectly well with the parallel earth paths, also the parallel earth paths actually make your reading look better?
But the one that threw me the most was, as long as they get a good reading on sometimes as little as 25% of the install, they pass it and just right only 25% checked in the limitations, and this is acceptable?
I'm just looking for some clarification, now i know none of the professional testers on this site would do such things so i'll phrase my question as; exatly what tests would your "friend" do and how would he do them? Thanks.