Hi folks,
Just wanted to check and see if bonding is required in this situation:
I'm erring on the side of not required, however if anyone could shed any light otherwise I'd be very grateful!
Tom
Just wanted to check and see if bonding is required in this situation:
- There's no bond to water pipework, bond to gas all present and correct
- There is a piece of plastic pipe at the point where the water enters the building, probably around 100mm in length
- There is then a mix of copper and plastic water pipework throughout the installation
- I don't think there's any metal water pipework which penetrates the floor at any point after the service comes into the building
- There is no continuity between any of the copper water pipework and the MET (Megger reads >99.9kOhm)
I'm erring on the side of not required, however if anyone could shed any light otherwise I'd be very grateful!
Tom