hello guys
I need some advice on and EICR job.
On the MET we have two main bonding conductors 10mm each.
Water is fine however I cannot find the gas bond connection on the pipe.
I know it is connected to the pipe as a long lead test gives me 0.02.
The pipes resistance rises as I disconnect the main bond and clamp between the met and gas pipe.
What would you guys advise as I cannot see the connection within 600mm of the Pipe.
Code 3 advise having the bond reinstalled?
I need some advice on and EICR job.
On the MET we have two main bonding conductors 10mm each.
Water is fine however I cannot find the gas bond connection on the pipe.
I know it is connected to the pipe as a long lead test gives me 0.02.
The pipes resistance rises as I disconnect the main bond and clamp between the met and gas pipe.
What would you guys advise as I cannot see the connection within 600mm of the Pipe.
Code 3 advise having the bond reinstalled?