Hi Everyone,
Has anyone had this situation. The main incomming supply is pme which is in a isolated building all on its own.There are 3 different buildings all isolated from each other.The buildings all have water supplies/gas.I am installing 3 separate supplies to these buildings with swa & separate cpc,back to the main incomming supply. Does the main bond to gas/water have to go back to the incomming supply from each building ??? They are quite a distance apart.Any ideas welcome.Or can they be connected to the local board ???
Has anyone had this situation. The main incomming supply is pme which is in a isolated building all on its own.There are 3 different buildings all isolated from each other.The buildings all have water supplies/gas.I am installing 3 separate supplies to these buildings with swa & separate cpc,back to the main incomming supply. Does the main bond to gas/water have to go back to the incomming supply from each building ??? They are quite a distance apart.Any ideas welcome.Or can they be connected to the local board ???