Maintenance responsibility | on ElectriciansForums

Discuss Maintenance responsibility in the UK Electrical Forum area at ElectriciansForums.net

Joined
May 17, 2018
Messages
213
Reaction score
27
Location
London
Hi can someone tell me the clear the legal requirements of someone carrying out maintenance for example changing over like for like. I have been told many different things for example if we change something like for like on a circuit and we notice something not quite right we can carry on with the job and fill out a minor works certificate stating what is wrong with the circuit as long as we make it no worse condition we found it it. I can understand if it’s immediate dangerous we should lock off and make safe. However if we are replacing something that falls into potentially dangerous such as non compliant ZS values that would require a fair amount of work ie new cables ran underground where do we stand? My concerns being from a maintenance background is some kits critical and can’t be locked off but where do I stand if I’m the last person working on it and have noticed this issue? Can you still keep things running as long as you’ve informed in writing of the potential dangers?
 
You're straying across all sorts of boundaries.
It will be different for different circumstances.

Your responsibility ends when you've documented the issue and passed it to either your Supervisor or employer or the property owner or Responsible person for the property or whoever you were instructed to report to when first being given the specific work.

Who's paying for the work.
Is it quoted by your employer with limits
Have they or the customer / building owner agreed to allow work to continue beyond the original job.
Do you or your employer need to submit quotes and receive authorisation for additional work.
Do you need permits or other permission to isolate / disable


This is all information you should have been given by your employer / building owner etc before any work started.
 
You're straying across all sorts of boundaries.
It will be different for different circumstances.

Your responsibility ends when you've documented the issue and passed it to either your Supervisor or employer or the property owner or Responsible person for the property or whoever you were instructed to report to when first being given the specific work.

Who's paying for the work.
Is it quoted by your employer with limits
Have they or the customer / building owner agreed to allow work to continue beyond the original job.
Do you or your employer need to submit quotes and receive authorisation for additional work.
Do you need permits or other permission to isolate / disable


This is all information you should have been given by your employer / building owner etc before any work started.
Sorry I’m probably overcomplicating it so my employer is the who the works for maintaining is carried out on industrial sites run by ourselves?
 
From a legal perspective I'd suggest having a read through regulations 3 and 4 from the Electricity at Work Regulations 1989 as that is the ultimate statutory legal document. It's relevant to some of your questions.

The best short answer I can give is that any new work should not give rise to something that would attract a C2 (potentially dangerous) or C1 (dangerous) code on a periodic inspection. If a circuit has a C2 or a C1 before you start, I wouldn't start. As above, reporting it is key.

In the example you mention (very high Zs) then that would be a C2 as fault protection is compromised and automatic disconnection of supply may not occur. I would not want be working on anything downstream of that. (If critical then maybe considering temporary options to buy time such as using RCD protection for fault protection and/or creating a TT setup are worth discussing.)
 
thank you guys! If we’ve worked on something though as in we’ve tested loop impedance ie switched off isolated did an (R1+R2) realised that was too high then would we be at fault for energising the circuit as we was the last person touching it or is this only a problem if we was to say change a faulty motor then realise S@&t the circuit has a high ZS?
 

Reply to Maintenance responsibility in the UK Electrical Forum area at ElectriciansForums.net

Similar threads

  • Question
The last couple of de-loops that I have been involved with had the single phase supply replaced with a three phase cutout (as I believe the DNOs...
Replies
5
Views
912
Thank you for your response. I really appreciate it.
Replies
13
Views
704

Recommended Sponsor News

  • Article
thanks for the clarification. ( also thanks to Dan. ).
Replies
6
Views
2K
  • Article
More info on link below http://sbsc.uk.net/
    • Like
2
Replies
22
Views
9K
  • Article
Happy Friday Everyone! Subscribe for more jokes direct to your mailbox or send us your own jokes to be in with a chance of featuring, by clicking...
    • Like
2
Replies
27
Views
6K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top