hi all
when you do a job that only requires a minor works certificate and you need r1+r2 reading say for a extra socket, do you just test the new cable going to the new socket for r1+r2 or go round the ring?
with the first one could'nt you just do an earth loop test at the socket your coming off to make sure there is an earth path.