Has anyone experience and pitfalls of the time and information required to apply for a G83/1-2
i have a client wishing to install 4 ground mounted systems near cottages he has.
They are all fed from the same transformer and there is no other PV systems on that transformer
Each cottage has an individual MPAN number.
Time is obv ticking and i am dealing with SP networks and i am concerned they kibosh the plans.
i have all the kit just need approval prior to start