Hi wondering if anyone uses the NAPIT desktop package?
Have started too and the EICR doesn't have the need for recording the main switch for each DB on a multiple DB installation.
Spoke with NAPIT and they confirm all they want is the main switch/isolator at the origin. Then each DB schedule/test results sheet just lists the total number of circuits, single or 3 phase and the then the circuits in use!
I am personally sure that the main switch details for each DB should be recorded along with Zs and PFC at each DB. The Zs readings I guess are recorded from the preceding item as the outgoing circuits Zs on results sheets but not PFC. Maybe I am in correct and not needed but it just seems strange that it is required if a single DB but bot for each DB if multiple ones!
Thoughts appreciated?
Have started too and the EICR doesn't have the need for recording the main switch for each DB on a multiple DB installation.
Spoke with NAPIT and they confirm all they want is the main switch/isolator at the origin. Then each DB schedule/test results sheet just lists the total number of circuits, single or 3 phase and the then the circuits in use!
I am personally sure that the main switch details for each DB should be recorded along with Zs and PFC at each DB. The Zs readings I guess are recorded from the preceding item as the outgoing circuits Zs on results sheets but not PFC. Maybe I am in correct and not needed but it just seems strange that it is required if a single DB but bot for each DB if multiple ones!