Belated Happy New Year everyone (this is my 1st thread of 2012)
I have 2 new builds to do and have a query about the DNO supply cable.
The customer has said that the DNO have told him to supply and install the supply cable and they will then join it to the grid and at the other end to the temporary board (that I'm fitting) for the site. The weird thing is they dont appear to have provided a specification for what type and size of cable they want? Whether they will supply an earth etc.
The supply in the area is overhead and the nearest transformer (where the DNO say the supply will come form) is about 1KM away. The supply cable from the transformer is to be laid underground.
Now maybe the customer hasn't told me everything but it does sound a bit odd that the DNO haven't supplied more info? I wondered what other peeps thought?
I have 2 new builds to do and have a query about the DNO supply cable.
The customer has said that the DNO have told him to supply and install the supply cable and they will then join it to the grid and at the other end to the temporary board (that I'm fitting) for the site. The weird thing is they dont appear to have provided a specification for what type and size of cable they want? Whether they will supply an earth etc.
The supply in the area is overhead and the nearest transformer (where the DNO say the supply will come form) is about 1KM away. The supply cable from the transformer is to be laid underground.
Now maybe the customer hasn't told me everything but it does sound a bit odd that the DNO haven't supplied more info? I wondered what other peeps thought?