Hi folks, I need some advice on getting a new build connected by the supplier.
I need to know the order of things,and at what point to contact them to come and connect.
I'm just about to start the 1st fix, there is a cut out in the external box but no meter.
What happens next?
Thanks
 
From experience in my area, they'll want to see a copy of the "dead" test results before they'll install the meter and connect you up, so end of 2nd fix really.
 
You could contact them about installing a temp supply.

Trouble is, it could still be a few weeks for them to get to do it.

Give them a call and they will come round and advise you accordingly.
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

YOUR Unread Posts

Daily, weekly or monthly email

Thread starter

Joined
Location
Bristol
Website
http://www.vectorelectric.co.uk

Thread Information

Title
New Build
Prefix
N/A
Forum
Australia
Start date
Last reply date
Replies
4
Unsolved
--

Advert

Thread statistics

Created
DaveVector,
Last reply from
JUD,
Replies
4
Views
1,057

Advert

Back
Top