Hi folks, I need some advice on getting a new build connected by the supplier.
I need to know the order of things,and at what point to contact them to come and connect.
I'm just about to start the 1st fix, there is a cut out in the external box but no meter.
What happens next?
Thanks
 
From experience in my area, they'll want to see a copy of the "dead" test results before they'll install the meter and connect you up, so end of 2nd fix really.
 
You could contact them about installing a temp supply.

Trouble is, it could still be a few weeks for them to get to do it.

Give them a call and they will come round and advise you accordingly.
 
So no tea, radio or battery charging then!

You could contact them about installing a temp supply.

Trouble is, it could still be a few weeks for them to get to do it.

Give them a call and they will come round and advise you accordingly.

Or get one of these....

Honda-Generator.jpg
 

Reply to the thread, titled "New Build" which is posted in Australia on Electricians Forums.

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Daily, weekly or monthly email

Back
Top