Hi all

Got to price for a new build bloke of 3 flats. irst time I have quoted a new build so was thinking three days first fix and two days secound fix does this sound about right?

The flats are two bedroom with three sockets in each room and centre light just basics really nothing fancy. I was thinking three weeks in total first and secound fix with two of us. Done new builds when on the books but not on my own so would be greatfull for any replys.

Thanks
 
We worked as a team of two on student apartments 3beds & ensuites.& 1 kitchen.

We didn't chop boxes in as dry liners were doing them.

We 1st fixed 3 a day.......2nd fix & test took just over a day per apartment
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread starter

Joined

Thread Information

Title
New build
Prefix
N/A
Forum
UK Electrical Forum
Start date
Last reply date
Replies
5
Unsolved
--

Advert

Thread statistics

Created
mcm,
Last reply from
p11jor,
Replies
5
Views
1,027

Advert

Back
Top