J
jjrideon
Hi,
I would really appreciate some advice on a complete rewire I've recently had done of my house as part of a complete back to brickwork refurbishment.
The work commenced back in Jan 2008, but was only completed in March 2009 due to all sorts of problems with the main contractor.
I've received the installation & test certs, as well as building reg approval now and thought everything was fine.
British Gas electricians came out to fix a minor problem as part of a homecare agreement and pointed out that not all the circuits were RCD protected as they should be under the current regs. I assumed that this was because the installation was designed to the 16th edition regs and therefore it was OK to finish it off to that standard. However, I went and checked the cert's and they state BS7671:2008 which is the 17th edition regs.
I spoke to the main contractor's electrician who first of all tried to say everything was done correctly, then when I pointed out that I agreed it was, but maybe the paperwork was just filled in wrong and could he sort it out he just muttered about opening a can of worms and everything was fine, he stood by his work, he wasn't going anywhere etc. etc..
So what would you advise me to do? What should the paperwork say? I just want to make sure everything is above board!
Thanks for your help.
JJ
I would really appreciate some advice on a complete rewire I've recently had done of my house as part of a complete back to brickwork refurbishment.
The work commenced back in Jan 2008, but was only completed in March 2009 due to all sorts of problems with the main contractor.
I've received the installation & test certs, as well as building reg approval now and thought everything was fine.
British Gas electricians came out to fix a minor problem as part of a homecare agreement and pointed out that not all the circuits were RCD protected as they should be under the current regs. I assumed that this was because the installation was designed to the 16th edition regs and therefore it was OK to finish it off to that standard. However, I went and checked the cert's and they state BS7671:2008 which is the 17th edition regs.
I spoke to the main contractor's electrician who first of all tried to say everything was done correctly, then when I pointed out that I agreed it was, but maybe the paperwork was just filled in wrong and could he sort it out he just muttered about opening a can of worms and everything was fine, he stood by his work, he wasn't going anywhere etc. etc..
So what would you advise me to do? What should the paperwork say? I just want to make sure everything is above board!
Thanks for your help.
JJ